CONSTRUCTION UPDATE AUGUST 2015 - GASCOIGNE

Posted by Gabrielle Patterson on Dec 4, 2015 3:51:17 PM

5 - Unnamed

 

Demolition Complete:

 Over the last month we have seen demolition complete, the finalisation of the piling works and associated capping beam (that sits upon the basement wall piles) and commencement of bulk excavation.

 3 - three digger busy     1 - two digger     2 - hole two digger

 

What's Next?

Over the coming weeks we will see the completion of excavation and ground works prior to the pouring of the first basement slab.

The tower crane is being erected late September.

Settlement:

At this point, settlement is scheduled for the third quarter of next year, 2016.

 

 



CONCLUSION:

 

Gabrielle Patterson

By: Gabrielle Patterson

Marketing & Communications

Topics: Projects

Recent Posts

Introducing Malvern & York, Glen Iris.

Aug 17, 2017 1:32:09 PM

Last chance to view the magnificent Luminary display!

Aug 17, 2017 11:43:41 AM

Investment Information Evening

Jun 6, 2017 10:27:49 AM

Customised Living in Port Coogee

May 31, 2017 10:30:00 AM

Thinking about downsizing?

May 24, 2017 4:30:13 PM

What lies in the heart of Port Coogee?

May 22, 2017 4:30:28 PM